Final account
The final account is the agreed statement of the total sum due under a construction contract, settling the contract sum, variations, claims and adjustments.
- The agreed final figure for everything due under the contract.
- It settles variations, provisional sums, claims and adjustments.
- Agreeing it releases the last of the money and closes the job.
The final account is the agreed statement of the total sum due under a construction contract. It settles everything: the original contract sum as adjusted, all variations, the expenditure of provisional sums, claims for loss and expense, any liquidated damages, and the release of retention.
Agreeing it closes the commercial life of the project. Until it is agreed, the job is still open, however finished the building looks.
What it contains
The starting point is the contract sum. From there:
Variations, valued and agreed. Every instruction, priced and settled.
Provisional sums, with each allowance removed and the actual valued cost substituted, or omitted entirely where the work was never instructed.
Loss and expense, where prolongation or disruption entitles the contractor to recovery beyond the direct value of changed work.
Liquidated damages, deducted where the project completed late without an extension of time covering the delay.
Retention, released in line with the contract.
Why it takes so long
Because it is where every deferred argument arrives at once.
Variations that were instructed but never priced. Claims submitted without the records to support them. Disruption everyone acknowledges and nobody quantified at the time. Extensions of time applied for late, or not at all. Each of these was easier to resolve in the month it happened than it is a year later with a dispersed team.
What actually decides the outcome
Contemporaneous records. Not the strength of the argument at settlement, but what was written down at the time.
A contractor who can produce the written instruction, the priced variation, the site records showing the disruption and the notice given under the contract is negotiating from evidence. One relying on recollection and a reconstructed narrative is negotiating from a much weaker position, and experienced quantity surveyors on the other side know exactly how to test which they are facing.
Cash pressure compounds it. A contractor who needs the money now will accept less than they are owed, and everyone in the room understands that.
The practical implication
Final account performance is decided months before the negotiation, by whether the project kept its records as it went. Instructions confirmed in writing. Variations priced when instructed rather than at the end. Notices served within the contract’s timescales. A CVR carrying value at what is genuinely recoverable rather than what was hoped for.
Keeping that trail against the project as it accumulates, so settlement is a reconciliation rather than an archaeology exercise, is what Sync’s cost tracking and financial reporting are built to support.
Common questions
How long does a final account take to agree?
Months, frequently longer, and on contested projects sometimes years. The contract will set out a timetable, and it is regularly overrun. The pace is set by how well documented the variations and claims are, and by how far apart the two positions start.
What goes into it?
The original contract sum, adjusted for all instructed variations, the expenditure of provisional sums against their allowances, fluctuations where they apply, any loss and expense claims, liquidated damages if the project was late, and the release of retention.
Why do contractors settle for less than they are owed?
Usually because of cash and evidence. The money is needed now, the records supporting the claim are thin, and a certain settlement today is worth more than an uncertain one after adjudication. A contractor with contemporaneous records and no immediate cash pressure settles considerably better.
What happens if agreement cannot be reached?
The contract's dispute resolution provisions apply. In UK construction that usually means adjudication first, which is fast and produces a binding decision that can later be revisited in arbitration or litigation. Most disputes stop at adjudication.
More Commercial terms
All 7 in this categoryKeep the paperwork where the work is
Sync keeps your health and safety records against the projects they belong to, with review dates tracked, so the current version is there when someone asks for it.