Provisional sum
A provisional sum is an allowance in the contract for work that cannot be fully defined at tender, replaced later by the actual cost of the work instructed.
- A placeholder allowance for work that could not be priced at tender.
- It is expended by instruction and replaced by the real cost.
- Defined sums carry programme risk; undefined ones do not.
A provisional sum is an allowance included in the contract sum for work that cannot be fully defined or measured when the contract is entered into. Later, the work is instructed, carried out, valued, and the actual cost replaces the allowance.
They exist because some things genuinely cannot be pinned down at tender. Below-ground conditions before opening up, the scope of repairs to an existing structure, a client requirement not yet designed. Better to carry an honest allowance than to price a fiction.
Defined and undefined
This distinction, drawn from the standard methods of measurement, decides where risk sits and is the source of most provisional sum disputes.
A defined provisional sum comes with enough information at tender that the contractor could reasonably allow for it in their programme and preliminaries: the nature of the work, where it fits in the sequence, its approximate scope. Because they could plan for it, they generally have no entitlement to extra time or prelims when it is instructed.
An undefined provisional sum does not. The contractor could not sensibly programme it, so when it is instructed they are normally entitled to an extension of time and the associated preliminaries alongside the value of the work.
The practical trouble is sums labelled defined that carry nowhere near enough information to have been programmed. That becomes an argument once the instruction lands, and the tender wording usually decides it.
How they are expended
The contract administrator issues an instruction. The work is then valued using the same principles as a variation: contract rates where they apply, fair valuation where they do not. The allowance comes out of the contract sum and the valued cost goes in.
If the work is never instructed, the allowance is simply omitted. A contractor treating unspent provisional sums as anticipated turnover is counting money that may never exist.
Keeping track of them
Provisional sums are easy to lose sight of because they sit quietly in the contract sum until something triggers them. Six months in, with several instructed and valued and others still outstanding, the question of what remains and what the instructed work actually cost against its allowance is one many projects struggle to answer quickly.
Recording each sum, its classification, the instruction that expended it and the resulting valuation keeps the CVR honest and makes the final account a reconciliation rather than an excavation. That is what Sync’s budget management and cost tracking are built to hold.
Common questions
What is the difference between defined and undefined provisional sums?
A defined provisional sum is described well enough at tender that the contractor could allow for it in their programme and preliminaries. An undefined one is not. That distinction matters because with an undefined sum the contractor is generally entitled to an extension of time and additional preliminaries when it is instructed, and with a defined one they are usually not.
How is a provisional sum different from a variation?
A provisional sum is anticipated at the outset, with money set aside for it in the contract sum. A variation is a change to the agreed scope arising later. When a provisional sum is expended the allowance is simply replaced by the actual valued cost, rather than being added on top.
Can a provisional sum be left unspent?
Yes. If the work is never instructed, the allowance is omitted from the contract sum entirely. The contractor has no entitlement to it, which is why relying on provisional sums as anticipated turnover is unwise.
Why do they cause disputes?
Because the classification is often loose. A sum described as defined but with insufficient information for the contractor to have programmed it properly becomes an argument about time and preliminaries once instructed, and the wording at tender decides it.
More Commercial terms
All 7 in this categoryKeep the paperwork where the work is
Sync keeps your health and safety records against the projects they belong to, with review dates tracked, so the current version is there when someone asks for it.