RAMS
Also known as: Risk Assessment and Method Statement
RAMS stands for Risk Assessment and Method Statement: two documents that set out the hazards of a task and the safe way to carry it out.
- Two documents, usually issued together before higher-risk work starts on site.
- The risk assessment lists the hazards and controls; the method statement sets out the safe sequence.
- Principal contractors normally require current RAMS from every subcontractor before they start.
RAMS is shorthand for a Risk Assessment and Method Statement, usually supplied together before higher-risk work begins on site. The risk assessment identifies the hazards, who could be harmed and the controls that will be used. The method statement sets out, step by step, how the task will be done safely using those controls.
The two are separate documents doing separate jobs, which is why the acronym is slightly misleading. One is an analysis; the other is an instruction. A risk assessment that never turns into a method the crew can follow has not achieved anything on site.
What goes in each document
The risk assessment works through the task and records what could go wrong: the hazards, who is exposed to them, how likely and how severe the harm would be, and what controls bring that down to an acceptable level. Controls should follow the hierarchy of control rather than reaching straight for PPE: eliminate the hazard if you can, substitute it if you cannot, engineer it out, then control it by how the work is organised, and only then rely on equipment worn by the person.
The method statement takes those controls and turns them into a sequence: what happens first, who does it, what plant and equipment is involved, what is checked before the next step begins. It is written to be followed by the people doing the work, which means it should read like instructions, not like a policy.
Where RAMS fit on site
Most principal contractors will not let a subcontractor start until they have accepted their RAMS. In practice it sits alongside a cluster of other paperwork: COSHH assessments for any hazardous substances, a permit to work where the task needs formal authorisation, and evidence that the crew have been briefed, often through a toolbox talk recorded against the job.
This is where RAMS most often goes wrong, and it is rarely the writing. It is version control. A set of RAMS written for the original sequence, superseded twice as the programme moved, and then produced from an inbox during an audit is worse than no RAMS at all, because it documents a method nobody followed. Keeping each project’s RAMS in one place, against the job, with review dates visible, is what makes the document worth having, and it is the part Sync’s risk management is built to handle.
Under CDM 2015 the principal contractor also has to be able to show how the work was planned, managed and monitored. Accepted RAMS, with the review history behind them, are a large part of that evidence.
Common questions
Is RAMS a legal requirement?
Not by that name. What the law requires is a suitable and sufficient risk assessment under regulation 3 of the Management of Health and Safety at Work Regulations 1999, and for that to be written down if you employ five or more people. The method statement is not a statutory document at all. RAMS as a paired deliverable is industry practice and, more often, a contractual condition: the principal contractor asks for it before you go on site.
Who writes the RAMS?
Whoever is carrying out the work. A subcontractor writes the RAMS for their own task because they are the ones who understand the method. The principal contractor reviews and accepts it, and checks it against the site's own arrangements, but writing it for you would defeat the point.
Is a RAMS the same as a COSHH assessment?
No. RAMS covers a task; a COSHH assessment covers a specific hazardous substance. Where a task involves one, the COSHH assessment is normally referenced by the RAMS and issued alongside it.
How often should RAMS be reviewed?
Whenever something material changes (the method, the materials, the people doing the work, the sequence, or the conditions on site), and immediately after any incident or near miss involving that task. A date-based review on its own is not enough if the job has changed in between.